Works | Stopped | Entry | Departure | Duration | Level of Work | Actual | Mileage |
---|---|---|---|---|---|---|---|
Gorton Works | 30/03/1907 | 11/05/1907 | 43 days | General | Boiler number 1207 (Diagram 16Sat) |
||
Gorton Works | 22/11/1910 | 04/02/1911 | 75 days | General | Boiler number 1214 (Diagram 16Sat) |
||
Gorton Works | 18/10/1913 | 22/11/1913 | 36 days | General | Boiler number 835 (Diagram 16Sat) |
||
Gorton Works | 04/09/1920 | 09/10/1920 | 36 days | General | Boiler number 498 (Diagram 16Sat) |
||
Gorton Works | 08/07/1922 | 30/09/1922 | 85 days | General | |||
Gorton Works | 29/11/1924 | 21/02/1925 | 85 days | General | Renumbered to LNER (1924) number 6095 |
||
Gorton Works | 09/07/1927 | 08/10/1927 | 92 days | General | Rebuilt to class B4/1 Boiler number 801 (Diagram 16Sup) |
||
Gorton Works | 05/04/1930 | 17/05/1930 | 43 days | General | |||
Gorton Works | 23/04/1932 | 28/05/1932 | 36 days | General | Boiler number 128 (Diagram 16Sup) |
||
Gorton Works | 20/05/1933 | 03/06/1933 | 15 days | General | Boiler number 684 (Diagram 16Sup) |
||
Gorton Works | 28/07/1934 | 04/08/1934 | 8 days | Light Repair | |||
Gorton Works | 12/01/1935 | 26/01/1935 | 15 days | General | Boiler number 922 (Diagram 16Sup) |
||
Gorton Works | 04/04/1936 | 25/04/1936 | 22 days | General | Boiler number 55 (Diagram 16Sup) |
||
Gorton Works | 23/05/1936 | 06/06/1936 | 15 days | Light Repair | |||
Gorton Works | 04/12/1937 | 25/12/1937 | 22 days | General | Boiler number 684 (Diagram 16Sup) |
||
Gorton Works | 07/10/1939 | 28/10/1939 | 22 days | General | Rebuilt to class B4/3 Boiler number 797 (Diagram 16Sup) |
||
Gorton Works | 06/01/1942 | 31/01/1942 | 26 days | General | |||
Gorton Works | 10/02/1944 | 10/02/1944 | 1 day | No repairs |
Date | Event | Details | Source | See Also |
---|---|---|---|---|
06/1906 | To Service | To service as Great Central Railway Number 1095 Built at Beyer Peacock Ltd., Works Number 4816 Diagram 16Sat boiler fitted |
||
30/03/1907 | Works Visit | Works Visit - Gorton Works (General) - Arr: 30/03/1907. Dep: 11/05/1907. Work undertaken: Boiler number 1207 (Diagram 16Sat) |
||
22/11/1910 | Works Visit | Works Visit - Gorton Works (General) - Arr: 22/11/1910. Dep: 04/02/1911. Work undertaken: Boiler number 1214 (Diagram 16Sat) |
||
18/10/1913 | Works Visit | Works Visit - Gorton Works (General) - Arr: 18/10/1913. Dep: 22/11/1913. Work undertaken: Boiler number 835 (Diagram 16Sat) |
||
04/09/1920 | Works Visit | Works Visit - Gorton Works (General) - Arr: 04/09/1920. Dep: 09/10/1920. Work undertaken: Boiler number 498 (Diagram 16Sat) |
||
08/07/1922 | Works Visit | Works Visit - Gorton Works (General) - Arr: 08/07/1922. Dep: 30/09/1922. | ||
08/12/1922 | Allocation | Reallocated to Sheffield Neepsend (SHF) | ||
01/1924 | Allocation | Reallocated to Mexborough (MEX) | ||
02/06/1924 | Allocation | Reallocated to Doncaster (DON) | ||
29/11/1924 | Works Visit | Works Visit - Gorton Works (General) - Arr: 29/11/1924. Dep: 21/02/1925. Work undertaken: Renumbered to LNER (1924) number 6095 |
||
19/02/1925 | Allocation | Reallocated to Gorton (GOR) | ||
16/05/1925 | Allocation | Reallocated to New England (NWE) | ||
19/01/1926 | Allocation | Reallocated to Copley Hill (Leeds) (COP) | ||
09/07/1927 | Works Visit | Works Visit - Gorton Works (General) - Arr: 09/07/1927. Dep: 08/10/1927. Work undertaken: Rebuilt to class B4/1 Boiler number 801 (Diagram 16Sup) |
||
05/04/1930 | Works Visit | Works Visit - Gorton Works (General) - Arr: 05/04/1930. Dep: 17/05/1930. | ||
23/04/1932 | Works Visit | Works Visit - Gorton Works (General) - Arr: 23/04/1932. Dep: 28/05/1932. Work undertaken: Boiler number 128 (Diagram 16Sup) |
||
24/10/1932 | Allocation | Reallocated to Neasden (NEA) | ||
15/12/1932 | Allocation | Reallocated to Immingham (IMM) | ||
09/05/1933 | Allocation | Reallocated to March (MAR) | ||
20/05/1933 | Works Visit | Works Visit - Gorton Works (General) - Arr: 20/05/1933. Dep: 03/06/1933. Work undertaken: Boiler number 684 (Diagram 16Sup) |
||
28/07/1934 | Works Visit | Works Visit - Gorton Works (Light Repair) - Arr: 28/07/1934. Dep: 04/08/1934. | ||
12/01/1935 | Works Visit | Works Visit - Gorton Works (General) - Arr: 12/01/1935. Dep: 26/01/1935. Work undertaken: Boiler number 922 (Diagram 16Sup) |
||
09/1935 | Allocation | Reallocated to Lincoln (LIN) | ||
04/04/1936 | Works Visit | Works Visit - Gorton Works (General) - Arr: 04/04/1936. Dep: 25/04/1936. Work undertaken: Boiler number 55 (Diagram 16Sup) |
||
23/05/1936 | Works Visit | Works Visit - Gorton Works (Light Repair) - Arr: 23/05/1936. Dep: 06/06/1936. | ||
07/07/1937 | Allocation | Reallocated to Immingham (IMM) | ||
02/09/1937 | Allocation | Reallocated to Lincoln (LIN) | ||
04/12/1937 | Works Visit | Works Visit - Gorton Works (General) - Arr: 04/12/1937. Dep: 25/12/1937. Work undertaken: Boiler number 684 (Diagram 16Sup) |
||
07/10/1939 | Works Visit | Works Visit - Gorton Works (General) - Arr: 07/10/1939. Dep: 28/10/1939. Work undertaken: Rebuilt to class B4/3 Boiler number 797 (Diagram 16Sup) |
||
28/10/1939 | Reinstated | Reinstated to Gorton (GOR) | ||
29/10/1939 | Allocation | Reallocated to Lincoln (LIN) | ||
06/01/1942 | Works Visit | Works Visit - Gorton Works (General) - Arr: 06/01/1942. Dep: 31/01/1942. | ||
16/08/1942 | Allocation | Reallocated to Langwith Junction (LNG) | ||
21/11/1942 | Allocation | Reallocated to Doncaster (DON) | ||
29/11/1942 | Allocation | Reallocated to Langwith Junction (LNG) | ||
20/02/1943 | Allocation | Reallocated to Ardsley (ARD) | ||
10/02/1944 | Withdrawn | Condemned as 6095 from Ardsley (ARD) | ||
10/02/1944 | Works Visit | Works Visit - Gorton Works (No repairs) - Arr: 10/02/1944. Dep: 10/02/1944. | ||
1946 | Number Allocated | Allocated number 1490 but not taken up |